Solving Big Challenge

Before the cold milling machines could begin their work, they were lifted onto the surface to be milled by lattice boom cranes

At an altitude of 235 m, the earthfill embankment dam on Lake Oroville dams the waters of the Feather River. After several weeks of rainfall, the dam reached its maximum water level of around 4.3 billion cu m in the winter after only 50 days. As a result, the owner, the California Department of Water Resources, had to initiate flood control measures at an early stage. The water was discharged in a controlled manner over the top of the dam structure at the level of the dam crown and the adjacent spillway. Due to the large quantities of water and the extremely high water pressure, however, the 55 m wide, main concrete spillway eroded to such an extent that rehabilitation was unavoidable. The damage was initially minimised provisionally by filling the erosion in the surface with rolled concrete, 鈥渟o that the owner could open the overflow system during the winter months, if necessary,鈥 explains Chris Anderson, Project Manager at the subcontractor, milling service provider Anrak. This temporary material had to be removed prior to final concrete paving with Portland cement, however, in order to achieve the desired surface quality. To complete this task, the contractor decided to use two cold milling machines from Wirtgen.

Steel cables attached to a wheel loader secured the Wirtgen cold milling machines

Built-in Wirtgen levelling system and milling drum design impress contractor
Eight days had been scheduled for the removal of the first layer of rolled concrete.
The lower section of the spillway was about 300 m long. The milling depth required was approximately 5 cm. This job was performed by the W 2100 equipped with an ECO cutter milling drum. This milling drum is fitted with up to 50 per cent fewer picks at larger tool spacing (LA) than a standard milling drum. Fewer picks means a lower cutting resistance, making it possible to mill hard surfaces such as concrete. This process was followed by the W 210i with a standard LA15 milling drum to give the milled surface the finer texture required to pave the new concrete layer. During the job, both machines used the Level Pro levelling system developed by Wirtgen. According to Tom Schmidt, CEO of Anrak, this is a perfect symbiosis: 鈥淲e have used almost every machine under the sun, but none can compete with the Wirtgen milling machine together with the Level Pro system. It is both reliable and extremely precise. The evenness of the surface is perfectly uniform and the machine always has excellent traction. The latter is important when milling rolled on Portland cement concrete. And the vibrations that are unavoidable when milling such a hard surface don鈥檛 affect the Level Pro system one bit.鈥

Safety played an important role during the rehabilitation project. In order to protect the workers and their equipment, cargo containers secured the lower end of the spillway

Logistical challenges
After the flat bed trucks had transported the cold milling machines to the upper end of the spillway, the machines were lifted onto the structure with the aid of lattice boom cranes and driven onto the area in need of rehabilitation via specially constructed ramps. Here, they faced the next challenge 鈥 milling on a 30-degree gradient. This challenge was solved by attaching steel cables with a total length of more than 450 m to the blades of a large wheel loader and to the rear of the large milling machines, thus securing the machines while work was being carried out. In the process, the heavy steel cables were attached to several hundred trolleys that are normally used for transporting heavy furniture in order to prevent them from rubbing against the ground. 鈥淲e used the trolleys to prevent the texture of the freshly milled concrete surface from being damaged,鈥 explains Tom Chastain, Applications Specialist at Wirtgen America.


At an altitude of 235 m, the embankment dam on Lake Oroville dams the waters of the Feather River. This makes it the highest dam in the US.

Application expertise and safety go hand-in-hand
The machines have a working width of 2.2 m, and it took an average of two hours to remove an entire length. 鈥淚n order to achieve the desired surface quality, and also for safety reasons, the cold milling machines were operated at a low advance rate of approx 3 m/minute,鈥 says Chastain. In the end, the W 2100 and the W 210i had each milled 28 full lengths. The cold milling machines loaded the milled material directly onto tracked vehicles with a capacity of 5 cu m. These machines are mainly used in open-cast mining, but their excellent maneuverability also made them valuable for steep gradient milling at the Oroville Dam. As soon as the tracked vehicles were filled, they unloaded the milled material at the lower end of the spillway so that it could be transported to a nearby concrete plant. There, the concrete milled material was reprocessed into new concrete for the subsequent construction project.

After the 鈥榤illing the spillway鈥 subproject had been reliably completed within the scheduled time frame, the entire rehabilitation project costing $1.1 billion was completed on schedule after around two years.